araphoe county logo
File #: 25-099    Version: 1
Type: Resolution Status: Passed
File created: 1/27/2025 In control: Board of County Commissioners Business Meeting
On agenda: 2/11/2025 Final action: 2/11/2025
Title: Grant of Easement for High Line Canal Trail Underpass at Yale and Holly
Attachments: 1. Board Summary Report, 2. Resolution

To:                                                               Board of County Commissioners

 

Through:                                          Gini Pingenot, Director, Open Spaces

 

Prepared By:

prepared

Michele Frishman, Grants and Acquisitions Manager, Open Spaces

end

 

Subject:

title

Grant of Easement for High Line Canal Trail Underpass at Yale and Holly

end

 

Purpose and Request:

recommended action

Staff requests that the Board of County Commissioners (BOCC) adopt a resolution authorizing an easement with the City and County of Denver for the construction and maintenance of a new High Line Canal trail underpass near the intersection of East Yale Avenue and South Holly Place and authorize the Open Spaces Director to sign the easement. Staff discussed the proposed easement with the BOCC on February 3, 2025.

end

 

Background and Discussion: The City and County of Denver plans to construct a new underpass for High Line Canal (HLC) trail users beneath East Yale Avenue and west of South Holly Place at the boundary of Arapahoe County and Denver. Arapahoe County and Denver Water, which has retained rights on the property, have reviewed and approved the construction plans; work is expected to begin in June 2025. Arapahoe County contributed $500,000 to the project; Denver is responsible for the remaining project costs.

A permanent easement and a temporary construction easement are needed for Denver to complete the project. BOCC authorization is only required for the grant of the permanent easement, which would allow Denver to construct, reconstruct, maintain, repair, and utilize a trail underpass, including retaining walls, pedestrian ramps, and appurtenances. Denver must maintain the installations at no expense to Arapahoe County, and the plans for any future work on the underpass must be approved by Arapahoe County.

Staff recommends issuing the easement at no cost because (1) the new underpass would provide significant benefits and improve safety for HLC trail users; (2) if Denver eventually takes ownership of the portions of the HLC corridor within its boundaries, the easement would automatically terminate; and (3) the easement would be non-exclusive, allowing Arapahoe County and other parties to continue to use the property.

 

Alternatives: The BOCC could modify or deny the issuance of the easement. 

 

Fiscal Impact: None.

 

Alignment with Strategic Plan:

                     Be fiscally sustainable

                     Provide essential and mandated service

                     Be community focused

 

Concurrence: None.

 

Resolution:  Attached is a copy of the draft resolution.