Legislation Details

File #: 26-479    Version: 1
Type: Presentation Status: Agenda Ready
File created: 9/14/2026 In control: Board of County Commissioners Study Session
On agenda: 9/28/2026 Final action:
Title: 1:30 PM *Waiver per Purchasing Policy for TruePoint Solutions
Attachments: 1. Board Summary Report, 2. Waiver per Purchasing Policies - Truepoint

To:                                                               Board of County Commissioners

 

Through:                                          Ceila Rethamel, Engineering Services Division Manager, Acting Director, Public Works and Development

 

Prepared By:

prepared

Amanda Feathers, Finance and Administration Manager, Public Works and Development

end

 

presenter

Presenter:                                          Katie Curtis, Support Services Division Manager, Public Works and Development

end

 

Subject:

title

1:30 PM *Waiver per Purchasing Policy for TruePoint Solutions

end

 

Purpose and Request:

recommended action

The purpose of this request is to add $25,000 to the waiver for TruePoint Solutions to cover the final implementation and support invoices for the Accela project. This increase will exceed the $100K limit and is necessary to ensure completion of the project as planned.

end

 

Alignment with Strategic Plan: Good Governance - Deliver mandated and essential services with excellence.                     

 

Background and Discussion: Accela is the primary operational application used by Public Works and Development (PWD); it is used by every PWD division in daily operations. Over the years since the initial implementation of Accela, the IT Department and PWD staff have worked on “remediation” projects to configure portions of Accela to meet the business needs of that area. However, as business needs have changed over the years and new programs have been implemented, a considerable backlog of enhancements has accrued that are needed in Accela to ensure efficiency in the County’s work. Making these enhancements to the Accela system allows the County to provide better service for its customers. 

 

Alternatives: No alternatives as this is IT’s sole vendor for this service.   

 

Fiscal Impact: The original request was approved for the amount of $100,000. Additional expenditure has become necessary to complete the scope of work as planned. Based on updated cost information, an additional $25,000 is required, bringing the total amount to $125,000. Approval of this increase will ensure continuity of services and prevent delays to scheduled work. Funding is available within the current budget, and the requested adjustment aligns with project needs and anticipated expenditure.

 

Alignment with Strategic Implementation Strategies: N/A

 

Staff Recommendation: Staff recommends the BOCC Chair sign the waiver for the additional $25,000.

 

Concurrence: N/A