File #: 24-514    Version: 1
Type: Resolution Status: Passed
File created: 9/9/2024 In control: Board of County Commissioners Business Meeting
On agenda: 9/24/2024 Final action: 9/24/2024
Title: USR24-001, USS Great Plains Solar LLC - Use by Special Review
Attachments: 1. Board Summary Report, 2. Staff Presentation, 3. Applicant's Presentation, 4. Staff Report, 5. Application and Referral Comments, 6. Referral Comments and Applicant's Response, 7. Engineering Staff Report, 8. Exhibit, 9. Draft Motions, 10. Resolution
To: Board of County Commissioners

Through: Bryan Weimer, Director of Public Works and Development

Prepared By:
prepared
Molly Orkild-Larson, Principal Planner, Public Works and Development
end

presenter
Presenter: Molly Orkild-Larson, Principal Planner, Public Works and Development
end

Subject:
title
USR24-001, USS Great Plains Solar LLC - Use by Special Review
end

Purpose and Request:
recommended action
The applicant, USS Great Plains Solar LLC, on behalf of the owner, Lowry Environmental Protection Cleanup Trust Fund, is seeking approval of a USR application for a 4.93 megawatt-alternating current photovoltaic solar energy generation facility to be located on a 106.5-acre parcel that is north and adjacent to E. Hampden Avenue and west of E-470. This facility will be located on the south portion of this parcel and south and adjacent to another solar facility (USS High Plains Solar) proposed on the property. The subject facility will contain PV panels, trackers, inverters, transformers, underground electric collection lines, access roads, and security fencing. The applicant is also requesting a reduction to the 2,000-foot setback from a Designated Outside Activity Area (DOAA). The DOAA is the Plains Conservation Center, which contains a visitor center, historic structures, and outbuildings used for public education, and is situated 1,051 feet west of the proposed facility.

The solar facility will obtain access from E. Hampden Avenue and is located within a fenced 30.4-acre lease area on the subject property. Both solar facilities will share the same access roads. The facility will operate unmanned with only infrequent operations and maintenance visits, and weekly site visits to check for trapped or injured wildlife. No water, sanitary sewer, phone, cable, or gas services are proposed for this project.
end

Background and Discussion: The parcel is vacant but has been farmed in the past. The applicant initially applied for Administra...

Click here for full text