File #: 22-667    Version: 1
Type: Resolution Status: Passed
File created: 11/8/2022 In control: Board of County Commissioners Business Meeting
On agenda: 11/22/2022 Final action: 11/22/2022
Title: C19-24 Utility Relocation Policy
Attachments: 1. Board Summary Report, 2. 2021 Utility Relocation Policy, 3. Revised 2022 Utility Relocation Policy, 4. Draft Motions, 5. Resolution
To: Board of County Commissioners

Through: Bryan Weimer, PWLF, Director, Public Works & Development

Prepared By:
prepared
Daniel Wiseheart, PE, CIP Project Manager
end

presenter
Presenter: Daniel Wiseheart, PE, CIP Project Manager
end

Subject:
title
C19-24 Utility Relocation Policy
end

Purpose and Request:
recommended action
Following the 2021 adoption of the Utility Relocation Policy, and direction from the Board of County Commissioners (BOCC), staff from Public Works and Development (PWD) have evaluated the policy for 1 year and now present updates to the policy to the BOCC for review and adoption.

PWD Staff presented updates and recommendations to the BOCC on October 4, 2022. The BOCC requested that PWD also present at a general business meeting.
end

Background and Discussion: In 2020 and 2021, a draft of the revised policy was circulated internally for review and comment to staff within PWD, and then externally for additional review and comments to Utility Providers, contractors, and other local jurisdictions. Comments from 2021 were received from 9 PWD staff members and from 4 external sources: Cherry Creek Valley Water and San, MCI/Verizon, Xcel Energy, and East Cherry Creek Valley Water and San. Both sets of review comments were discussed, and appropriate revisions made, as needed. The final draft of the Policy was then sent to the Director of PWD and Arapahoe County Attorney's Office for final review. All comments have been addressed and final edits have been made. Presented here within is the final policy document for BOCC review and adoption. Since the 2021 adoption, the policy has not been exercised as it relates to the cost sharing of utility relocations. However, PWD Staff have been working on supporting documents, accompanying SOP, and minor edits to the policy. PWD Staff feel that the creation and maintenance of such documents is an iterative process, and the first iteration of such is hereby presented to the Board.

Al...